|
Construction of the Dam
commenced on 26/5/ 2003 and will continue until late 2005.
Located on Yarmouk River,
which forms part of the northern boundaries of Jordan with Syria, at about
120 Km from Amman the Capital.
It is
a gravity Roller Compacted Concrete (RCC) dam and to be constructed in two
stages. The first stage is to bring the dam’s crest to Elevation 116 m
a.s.l and the maximum normal water level to El. 110. The total storage
capacity would be about 110 MCM (Million Cubic Meters). The second stage
is to raise the dam, in the future, to Elevation 140 m a.s.l with a total
storage capacity of about 225 MCM.
The
dam will capture the floods and available base flow in the Yarmouk basin
and hence will:
-
Provide about 30 MCM of
water to irrigate 31000 dunums (1 dunum = 1000 m2) of
cultivated land.
-
Supply Amman and its
vicinity by about 50 MCM/ year of potable water.
-
Generate yearly about
18,800 Megawatt/hr of electricity after the second stage is completed.
Expected Construction
Cost and Financing of the Project:
Cost and time for
construction of RCC dams is noticeably low, hence in 1999 Jordan Valley
Authority (JVA) awarded three RCC dam projects namely Almujib, Wala
and Tannur. JVA reconsidered RCC for Al-Wehdah dam design
and based on the cost of above projects it is estimated that the expected
cost of the first stage of construction, i.e. building the dam to El. 116
only, is about 66 MJD (Million Jordan Dinars) including consultants’ fees
for change of design and supervision over construction.
The following agencies will
finance the project with about 89 Million JOD (MJD):
-
The Arab Fund for Economic
and Social Development (shall cover 80% of the total cost of the
Project),
-
Abu Dhabi Fund for
Development (10%) and
-
The Government of Jordan.
The Consultant:
On 18/3/2002 Harza
Engineering was awarded the contract for the redesign and later the
supervision over the construction of the project for a total cost of
3687550 JD.
The Construction
Contract:
On 20/7/2002 seven
Contractors were prequalified to apply for the construction of Al-Wehdah
dam project. Six Contractors purchased the Contract documents and Five
Contractors applied for bidding on 1/12/2002. The Contract was awarded to
the Turkish Company Özaltin in February 2003 for about 62 million
Jordanian Dinars. The Contract agreement was signed with them on 6/4/2003
and the order to commence the Construction works was issued on 26/ 5/
2003.
Principal Features of
the Project
The Al-Wehdah Dam Project
consists of the following principal features:
-
An Existing Diversion
Tunnel in the right abutment Length = 950 m, modified horseshoe shape,
Diameter = 7.75 m, slope = 0.0138 and Capacity (Design Flood) 825 m3/s.
-
Excavation.
-
A Roller Compacted
Concrete (RCC) dam, Crest El. 116 raisable in the future to El. 140.
-
Grouting and drainage
galleries.
-
Grout curtain.
-
An Ungated stepped
Spillway over the RCC dam with an Ogee crest, invert El. 110.
-
A multi level intake tower
structure on the upstream face of the dam.
-
A discharge structure
downstream of the dam.
-
Conduits, 3.0 m diameter
each, for irrigation supply and future power generation.
-
Instrumentation for
monitoring dam behavior.
-
Access roads to major
features of the project.
-
Employer- Engineer Site
Offices and Accommodation.
AlWehdah Dam Description:
|
Feature |
The
Description |
|
Dam Crest |
El. 116.0 ASL (Av. Sea Level) |
|
Spillway
Invert Level |
El. 110.0ASL |
|
Total
Storage Capacity |
110 MCM |
|
Reservoir
top Surface Area |
4 Km2 |
|
Catchment
(Drainage) Area |
5900 Km2 |
|
Probable
Maximum Flood Flow (PMF) |
7940 m3
/s |
|
100-year
Design Flood Flow |
1200 m3
/s |
|
Annual
Average Flow, Yarmouk River, at Al-Wehdah dam site |
160 MCM / yr |
|
Width of Dam
at the Crest |
8 m |
|
Width of Dam
at El. 20 (lowest foundation level) |
110 m |
|
Length of
Dam at the Crest |
485 m |
|
Spillway width |
250 m |
|
Volume of
RCC |
1.3 MCM |
|
Upstream
face of the dam is vertical from El. 116 to El. 65, and then it is
with slope 1: 0.6 up to El. 20.
Downstream
face is with slope 1: 0.8 from El. 116 to El. 20.
|
|
Diversion
during construction: A Cofferdam (Contractor’s responsibility) and
the Existing Diversion Tunnel. |
For further information
contact
Jordan Valley Authority
Secretary General
Eng.
Zafer Alem E-mail:
Zafer,alem@mwi.gov.jo |