05-Water   Jordan Rift Valley Improvement Project SCENARIO: A RESP.AGENCY: JVA
PROJECT DATA SHEET
A. Description
The Government of Jordan is concerned that the Valley must continue to play a vital role in the development of the country, and has requested assistance with the reassessment of the Jordan Rift Valley Development, followed by support for investments and i
B. Yield Prod Saved C. Water Allocation (Mm3/yr)
     Water Volume (Mm3/yr) 28 17 Municipal 0% 0.0
Industrial 0% 0.0
D. Total Project Capital Costs 56 0 Irrigation 100% 44.5
     Plan Capital Costs (2001 JD m.)   56
          Local Cost Component 46% 26
          Foreign Exchange Component 54% 30 E. Recurrent Cost (JD m.)
          Duties & Taxes 0% 0 O&M 20.0% 11.20
F. Implementation Schedule 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016
     Project Year   1 2 3 4 5 6 7 8 9 10 11 12 13 14
     Capital Outlay 0% 21% 38% 34% 7% 0% 0% 0% 0% 0% 0%
     Water Yield/Revenues 0% 0% 21% 59% 93% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%
G. Project Status Feasibility Studies Final Design Tender Documents
     Financing: World Bank - Japan PHRD, GEF World Bank - Japan PHRD, JEF & Others World Bank - Japan PHRD, JEF & Others
     Completion Date 01-99 12-02 03-03
H. References & Comments 0
I. Anticipated Financing Sources JD m.
     Govt. of Jordan 26.0 46%
     Private Sources/Consortium 0 0.0 0%
     Country/Institution WB,USAID,KFW,GEF 30.0 54%
     Total Identified Funding 56.0  
     Total Un-Identified Funding 0.0  
05-Water   Jordan Rift Valley Improvement Project SCENARIO: A RESP.AGENCY: JVA
PROJECT ANALYSIS : SUMMARY 
2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016
A.  WATER QUANTITIES (Mm3/Yr)
     Produced 0 0 9 26 41 45 45 45 45 45 45 45 45 45 45
     Delivered 0 0 7 20 32 35 35 36 36 37 37 38 39 40 40
     Billed 0 0 2 7 12 14 15 16 17 18 19 20 20 21 21
     Available for Treatment & Reuse 0 0 -1 -3 -6 -7 -7 -8 -8 -9 -9 -10 -11 -12 -12
B. FINANCIAL  (Constant 2001 JD m.)
     Costs 0 12 21 19 4 0 0 0 0 0 0 0 0 0 0
    Revenues 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1
     Net Cash Flow 0 -14 -28 -29 -15 -11 -11 -11 -11 -11 -10 -10 -10 -10 -10
                               
  FIRR NM    PV of Costs (Fin.)   Water Produced AIC Water Delivered AIC
      JDm     Mm3 /m3   Mm3 /m3
  NPV 8% -114   PVC 8% 117   PPQ 8% 258 0.45 PDQ 8% 210 0.56
  NPV 10% -102   PVC 10% 105   PPQ 10% 220 0.48 PDQ 10% 179 0.59
  NPV 12% -92   PVC 12% 94   PPQ 12% 189 0.50 PDQ 12% 153 0.61
                               
C. ECONOMIC  (Constant '99 JD m.)
     Costs