01-TA   Water Feasibility, Design and Assessment Studies SCENARIO: A RESP.AGENCY: WAJ
PROJECT DATA SHEET
A. Description
In order to implement future water projects outlined in the investment program, there is a need to carry out feasibility studies, develop detailed designs, and prepare tender documents for the proposed projects. Under this assistance those studies will be
B. Yield Prod Saved C. Water Allocation (Mm3/yr)
     Water Volume (Mm3/yr) 0 0 Municipal 0% 0.0
Industrial 0% 0.0
D. Total Project Capital Costs 26 0 Irrigation 0% 0.0
     Plan Capital Costs (2001 JD m.)   26
          Local Cost Component 0% 0
          Foreign Exchange Component 100% 26 E. Recurrent Cost (JD m.)
          Duties & Taxes 0% 0 O&M 0.0% 0.00
F. Implementation Schedule 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016
     Project Year 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
     Capital Outlay 10% 10% 10% 10% 10% 10% 10% 10% 10% 10% 0%
     Water Yield/Revenues 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% 100% 100% 100% 100%
G. Project Status Feasibility Studies Final Design Tender Documents
     Financing: 0 0 0
     Completion Date 01-00 01-00 01-00
H. References & Comments 0
I. Anticipated Financing Sources JD m.
     Govt. of Jordan 0.0 0%
     Private Sources/Consortium 0 0.0  
     Country/Institution USAID,KFW and EIB 18.0 69%
     Total Identified Funding 18.0  
     Total Un-Identified Funding 8.0  
01-TA   Water Feasibility, Design and Assessment Studies SCENARIO: A RESP.AGENCY: WAJ
PROJECT ANALYSIS : SUMMARY 
2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016
A.  WATER QUANTITIES (Mm3/Yr)  
     Produced 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
     Delivered 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
     Billed 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
     Available for Treatment & Reuse 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
 
B. FINANCIAL  (Constant 2001 JD m.)  
     Costs 3 3 3 3 3 3 3 3 3 3 0 0 0 0 0
    Revenues 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
     Net Cash Flow -3 -3 -3 -3 -3 -3 -3 -3 -3 -3 0 0 0 0 0
                               
  FIRR NM    PV of Costs (Fin.)   Water Produced AIC Water Delivered AIC
      JDm     Mm3 /m3   Mm3 /m3
  NPV 8% -17   PVC 8% 17   PPQ 8% 0 NM PDQ 8% 0 NM
  NPV 10% -16   PVC 10% 16   PPQ 10% 0 NM PDQ 10% 0 NM
  NPV 12% -15   PVC 12% 15   PPQ 12% 0 NM PDQ 12% 0 NM
                               
C. ECONOMIC  (Constant '99 JD m.)