|
Al-Wihdeh Dam
Construction of
the Dam commenced on 26/5/ 2003 and will continue until
late 2005.
Located on Yarmouk
River, which forms part of the northern boundaries of
Jordan with Syria, at about 120 Km from Amman the
Capital. It is a gravity Roller Compacted Concrete (RCC)
dam and to be constructed in two stages. The first
stage is to bring the dam’s crest to Elevation 116 m
a.s.l and the maximum normal water level to El. 110.
The total storage
capacity would be about 110 MCM (Million Cubic Meters).
The second stage is to raise the dam, in the future, to
Elevation 140 m a.s.l with a total storage capacity of
about 225 MCM.
The dam will
capture the floods and available base flow in the
Yarmouk basin and hence will:
-
Provide about 30 MCM of water to irrigate 31000
dunums (1 dunum = 1000 m2) of cultivated
land.
-
Supply Amman and its vicinity by about 50 MCM/ year
of potable water.
-
Generate yearly about 18,800 Megawatt/hr of
electricity after the second stage is completed.
Expected Construction Cost and Financing of the Project:
Cost and time for construction of RCC dams is noticeably
low, hence in 1999 Jordan Valley Authority (JVA) awarded
three RCC dam projects namely Almujib, Wala and Tannur.
JVA reconsidered RCC for Al-Wehdah dam design and based
on the cost of above projects it is estimated that the
expected cost of the first stage of construction, i.e.
building the dam to El. 116 only, is about 66 MJD
(Million Jordan Dinars) including consultants’ fees for
change of design and supervision over construction. The
following agencies will finance the project with about
89 Million JOD (MJD):
-
The Arab Fund for Economic and Social Development
(shall cover 80% of the total cost of the Project),
-
Abu Dhabi Fund for Development (10%) and
-
The Government of Jordan.
The
Consultant:
On 18/3/2002 Harza Engineering was
awarded the contract for the redesign and later the
supervision over the construction of the project for a
total cost of 3687550 JD.
The
Construction Contract:
On 20/7/2002 seven Contractors were
prequalified to apply for the construction of Al-Wehdah
dam project. Six Contractors purchased the Contract
documents and Five Contractors applied for bidding on
1/12/2002. The Contract was awarded to the Turkish
Company zaltin in February 2003 for about 62 million
Jordanian Dinars. The Contract agreement was signed with
them on 6/4/2003 and the order to commence the
Construction works was issued on 26/ 5/ 2003.
Principal Features of the Project
The Al-Wehdah Dam Project consists of the following
principal features:
-
An
Existing Diversion Tunnel in the right abutment
Length = 950 m, modified horseshoe shape, Diameter =
7.75 m, slope = 0.0138 and Capacity (Design Flood)
825 m3/s.
-
Excavation.
-
A
Roller Compacted Concrete (RCC) dam, Crest El. 116
raisable in the future to El. 140.
-
Grouting and drainage galleries.
-
Grout curtain.
-
An
Ungated stepped Spillway over the RCC dam with an
Ogee crest, invert El. 110.
-
A
multi level intake tower structure on the upstream
face of the dam.
-
A
discharge structure downstream of the dam.
-
Conduits, 3.0 m diameter each, for irrigation supply
and future power generation.
-
Instrumentation for monitoring dam behavior.
-
Access roads to major features of the project.
-
Employer- Engineer Site Offices and Accommodation.
AlWehdah Dam Description:

|